Implementation of the 2nd new luggage conveyor of arrival area in Tahiti-Faa'a

Implementation of the 2nd new luggage conveyor of arrival area in Tahiti-Faa'a
05/04/2017
Started in 2014, the works of extension and refitting of the international arrival area are continuing with the end of the 3rd stage and the implementation of the 2nd luggage delivery belt on April 5th. The Passport control booths were also renewed and delivered at the same time.

Stage 4, the last one, began a few days ago with an objective to end the project in September. The total investment amounts to € 5.3M. The Arrival area is now sized to handle simultaneously 2 long range aircrafts with level B of IATA comfort standards.